- Title: Riverside Television Studio 1
- Completion date: September 2019
- Area: 605 sq m
The concrete floor was prepared using vacuum contained shot-blasting to clean and key the surface.
The Elgood Universal Television Studio Floor.
We were employed directly by Riverside TV.
The Main Contractor was Mount Anvil. To qualify to work on site, we had to meet the strict Health and Safety criteria of Mount Anvil including Critical Health Certificates for our in-house plant operators.
The installation was completed on schedule by our small team of full time employees.
Fire Lanes were installed along with a grid with numerals and 0.5 metre markers.
Riverside Television have new facilities at their historic base in Hammersmith, London.
We were selected by Riverside TV to install our Universal Studio Floor in their exciting studio complex. Studio 1 is the first of three to be installed.